Van's directions said that while the bulkhead was open, now would be a good time to fit the Wd-610 control column and the Wd-611/612 control stick bases. I pulled out the DWG 38 which shows the assembly and followed those instructions. Once I got them assembled I removed them as a unit leaving the mounts bolted to the bulkhead.
Today: 4 hrs
Fuselage: 44 hrs
Wings: 148 hrs
Empennage: 195 hrs
Total time on project: 388 hrs